Structural Frame Erection
Columns, beams, girders and bracing set, plumbed and bolted for warehouse, retail, office and light industrial shells across Greater Houston.
Commercial & Industrial Steel
Field erection of structural steel across Greater Houston. Crane picks, columns and beams set and plumbed, high-strength bolting, AWS D1.1 field welds, joists and deck, all by our own crews.

Service Overview
A steel frame goes up once, and every trade behind it waits on the crane. If the anchor bolts sit outside tolerance or the bolting fails special inspection, the columns land out of plumb and deck, roof, slab and MEP all stop with the frame. Steel set, plumbed and bolted to AISC tolerance the first time keeps that from happening. Jimenes Construction is a self-performing steel erector with 23 years on Houston job sites. Our own raising gangs rig, set, plumb, bolt and weld the frame for general contractors, developers, plant owners and facility managers, with no brokered crews and no hand-offs.
We erect what our shop fabricates and what other shops fabricate. That covers columns, beams and girders, braced and moment frames, joists and deck, pre-engineered metal buildings, mezzanines, pipe racks and equipment structures. If the steel still has to be detailed, cut and welded, start on our steel fabrication page. For the full package from shop drawings through turnover, see structural steel.
Erection starts at the concrete. Columns land on anchor bolts cast into a foundation on expansive Houston clay. We survey the bolt pattern and base plate elevations before steel ships, then shim to AISC 303 tolerance instead of forcing the frame. If the foundation is still ahead of you, our concrete foundation crews set those anchor bolts straight off the steel drawings.
Coverage
Each of these carries its own rigging, its own crew and its own inspection. We run all six in house.
Columns, beams, girders and bracing set, plumbed and bolted for warehouse, retail, office and light industrial shells across Greater Houston.
Pick plans by weight, radius and boom length, with qualified riggers and signal persons on tight urban lots and inside working Ship Channel plants.
Bolt pattern and elevation survey, leveling nuts and shim packs, grouted base plates set to AISC 303 tolerance on Houston clay foundations.
A325 and A490 connections installed to the RCSC spec by turn-of-nut or TC snap-off, with pretension verified before the inspector arrives.
Bar joists and joist girders landed, bridged and welded, then roof and floor deck fastened so the roofers and slab crew can follow the frame.
Moment connections, stiffeners, embeds, lintels, stairs and rails welded in place by AWS D1.1 qualified welders, with weld maps kept on site.
Our Process
Five steps, the same on a 40-ton mezzanine and on a 600-ton distribution frame. Call (832) 576-3278 to start at step one.
We read the approved shop and erection drawings. Then we survey the anchor bolt pattern, embeds and base plate elevations against AISC 303 tolerance before steel ships.
Pick weights and radii pick the crane. We map access, laydown and the raising sequence, pull lane closures where the lot is tight, and write the OSHA Subpart R erection plan.
Loads arrive in raising order, with piece marks and mill test reports checked at the gate. Columns, beams and girders are then landed and temporarily bolted, with fall protection in place.
The frame is plumbed and aligned with guys and turnbuckles. Bolts are tightened by turn-of-nut or TC snap-off. Moment welds are run by qualified welders.
Joists and deck are set and fastened, then third-party special inspection of bolts and welds is completed. Windstorm inspection is cleared where it applies. Punch list closed and reports filed.
Timeline
Real ranges from our own job records, from first pick to inspection sign-off.
| Project Type | Typical Size | Duration |
|---|---|---|
| Mezzanine or equipment platform frame | 1,000 - 4,000 sq ft | 3 - 7 Days |
| Pre-engineered metal building frame | 10,000 - 30,000 sq ft | 2 - 4 Weeks |
| Warehouse or distribution shell | 50,000 - 150,000 sq ft | 5 - 10 Weeks |
| Multi-story structural frame | 3 - 6 floors | 6 - 12 Weeks |
| Pipe rack or process equipment structure | 50 - 300 tons | 4 - 9 Weeks |
Engineering & Compliance
Houston steel has to answer to hurricane wind, salt air and a foundation that moves. We plan every erection around those three conditions.
Why Jimenes
Erection goes wrong at the hand-offs: one outfit rigs, another bolts, a third welds. Our own raising gang, bolt-up crew and welders work the frame start to finish.
We have set frames on Ship Channel plants, Grand Parkway warehouses and downtown infill lots. We know which picks the wind takes away and which sites need night work.
Bolt patterns, embeds and base plate elevations get checked while the foundation crew is still on site. A bad bolt group turns into a repair plan days before the crane shows up.
Tonnage, piece count, crane time, bolt-up, field welding and deck each get their own line. Change orders are priced and signed before the crew touches them.
Credentials
Texas does not license steel contractors or general contractors, so we send the insurance certificate, welder qualification records and inspection reports with every proposal. Here is what a steel erector in Houston can actually show you.
Where We Work
Headquartered in Houston and erecting steel across the Greater Houston area, from inside the 610 Loop out past the 180-mile Grand Parkway and east to the Ship Channel. If you searched for a steel erection contractor near me and landed here, this is the radius we cover. We can be on site the same week.
Good Questions
Still not sure? Call and talk to the person who will run your raising gang.
Talk to a BuilderErection is usually priced by the ton, and the rate moves with how hard the steel is to reach and set. Five things drive it: tonnage and piece count, crane size and access, and connection type (bolted, field welded or both). Height and shift matter too, along with how much laydown room the site gives us. Five hundred light pieces cost more to set than two hundred heavy ones, so we price piece count along with weight. Send us the erection drawings and you get a line-item number, never a flat rate. Fabrication is quoted on its own, on our steel fabrication page.
The concrete contractor sets them, and the erector lives with them. AISC 303 allows about 1/8 inch between rods inside a group, 1/4 inch from the established column line, and 1/2 inch on the top elevation of the rods. We survey every pattern before steel ships, so an out-of-tolerance group becomes an engineer-approved repair detail instead of a lost crane day. When we hold both scopes, our concrete foundation crews set the anchor bolts straight off the steel drawings.
Piece count and crane access set the schedule more than tonnage alone. A mezzanine frame can be standing in a week. A 100,000 square foot warehouse frame usually runs 5 to 10 weeks from first pick through deck. Bar joists and metal decking follow the raising gang bay by bay, so roofing starts before the last connection is welded. You get a dated erection schedule at contract.
We coordinate it, we do not self-certify it. A third-party agency inspects high-strength bolting and welds under IBC Chapter 17, and their reports go to the building official. On our side, welders hold current AWS D1.1 qualifications. A325 and A490 bolts are installed to the RCSC spec by turn-of-nut or TC snap-off, and mill test reports are collected for every member. All of it lands in the closeout package.
Yes. Hurricane season runs June 1 through November 30. We watch wind limits on every pick all season. Loose steel and partly braced frames get secured before a system moves in. East of SH 146 in Harris County, and in Galveston, Brazoria and Chambers counties, the TDI windstorm inspector has to see the connections before the WPI-8 certificate is issued. That inspection sits on the schedule from day one. Metal buildings in that zone get the same treatment.
Both. We erect steel from any fabricator, and we check piece marks, mill test reports and approved shop drawings at the gate before anything is picked. For frames already up, see steel repair and field modifications for reinforcing, cutting in openings and adding beams. For new floor area inside an existing building, see mezzanines. Call (832) 576-3278 and we will look at your drawings.